Successful Completion of Dry Test for 9.7 MW Upper Ingwa Khola Small Hydropower Project

Wed, Feb 7, 2024 3:57 PM on Latest,

The commercial production for Ingwa Hydropower Limited (IHL), where Api Power Company Limited (API) holds a majority share investment, is set to commence by the end of Falgun 2080. Ingwa Hydropower is overseeing the construction of the 9.7 MW Upper Ingwa Khola Small Hydropower Project, located on the Ingwa River in Panchthar district. API has invested 15 crore rupees worth of founding shares in Ingwa Hydropower Limited. Mr. Dwarika Prasad Neupane, Director of Api Power Company Limited, expressed confidence that the project would yield significant profits for API upon its completion.

Mr. Gokul Pandey, the finance manager of Ingwa Hydropower Limited, reported that the Upper Ingwa River Small Hydropower Project successfully completed its dry test on Magh 19, 2080. Mr. Pandey further mentioned that the charging of the transmission line is expected to be completed within the next week.