No revenue for Upper tamakoshi in Q2; What is the project status?

Thu, Feb 11, 2021 8:04 AM on Latest, Company Analysis,

Upper Tamakoshi Hydropower Limited (UPPER) has reported a net loss of Rs. 3.15 crores in this quarter.

As per the management, the Upper tamakoshi project of 456 MW is in the final phase of completion which is why the company has not earned any revenue till the date.

Its reserve fund stands at Rs. -82.20 crore with share capital at Rs 10.59 Arba.

The company sits in a liquidity position of 0.36 times. The acceptable ratio is 1.5 times.

Its annualized earning per share stands at Rs. -0.60. The net worth per share at Rs. 92.24.

Click here for Q2 report

Major Highlights:

Particulars

Upper Tamakoshi Hydropower Limited

Q2, 2077/2078

Q2, 2076/2077

Difference

Paid-Up Capital

10,590,000.00

10,590,000.00

-

Reserve & Surplus

-822,042.16

-662,151.39

-

Plant, Property and Equipment

6,381.21

7,496.51

-14.88%

Capital work in progress

81,011,196.17

72,043,654.41

12.45%

Investment in Associates

0.00

0.00

-

Borrowings

42,833,098.12

38,550,000.00

11.11%

Total Income

0.00

0.00

-

Administrative Expenses

22,562.03

24,874.85

-9.30%

Financial Expenses

11,250.00

1,111.13

912.48%

Net Profit

-31,571.08

-23,339.31

-

Earnings per share (Rs.)

-0.60

-0.44

-

Net worth per share (Rs.)

92.24

93.75

-

P/E Ratio (times)

-830.20

-

-

Current Ratio (times)

0.36

-

-